Delivered output; final cost unresolved1st Avenue South public parking garage
Verified: The City approved a construction-phase GMP of $17,219,706. At groundbreaking, the City described a design capacity of 365 spaces.
Not established: The reviewed sources do not establish final paid cost, closed-out change-order total, current as-built capacity, occupancy, utilization or cost per space.
CRA-S09 · CRA-S10Phase 1 grant-application services authorizedFifth Avenue South design decision
Verified: The April 3, 2025 minutes establish the three motions and named votes shown above. Resolution 2026-15857 later authorized a $310,702 Phase 1 agreement with Kimley-Horn plus a $20,000 owner's contingency allowance, for total authorized exposure up to $330,702.
Not established: The cited resolution did not authorize the separately scoped Phase 2 design and permitting work. These records do not establish construction, final cost, completion or individual motive.
CRA-S05 · CRA-S17 · CRA-S18Applications reportedRiver Park residential improvement program
Verified: At the April 3, 2025 meeting, the CRA administrator reported five applications received in 2024. In the same meeting, the chair orally referenced 32 qualifying homes.
Not established: Applications and potentially qualifying homes are different measures. The meeting record does not support publishing a participation percentage, completed-home count or beneficiary count from those two figures.
CRA-S05 · CRA-S11Consultant procurement and selectionRiver Park East infrastructure improvements
Verified: The July 2026 procurement record identifies Pape-Dawson as the selected firm and records a notice of intent to award professional engineering services.
Not established: The reviewed record does not establish an executed fee agreement, board-approved contract amount, construction award, construction spending or completed infrastructure result.
CRA-S19 · CRA-S20 · CRA-S21Authorized purchase and audited acquisition expense170 10th Street North land acquisition
Verified: The January 11, 2024 City Council minutes authorize a $4.9 million purchase of approximately 0.568 acres. The FY2024 audited CRA statements report a $4,910,196 acquisition expense.
Not established: The reviewed records do not by themselves establish a completed public project or long-term delivery result on the acquired site.
CRA-S07 · CRA-S15Negotiation and condition assessmentStillwater Cove acquisition discussion
Verified: City-hosted April 3, 2025 minutes marked DRAFT report a $23.5 million seller counter, an approximately $4.8 million consultant estimate to correct deficiencies, 95 units and 13 structures described as 56 years old.
Not established: The record does not establish a completed acquisition. City records also conflict on unit count and acreage, so no definitive acreage is published here.
CRA-S05 · CRA-S23