Delivered output; final cost unresolved1st Avenue South Public Parking Garage
Verified: The City approved a construction-phase GMP of $17,219,706 by Resolution 2023-0078 on October 12, 2023.
Not established: The reviewed sources do not establish final paid cost, closed-out change-order total, current as-built capacity, occupancy, utilization or cost per space.
CRA-S25 · CRA-S10Phase 1 grant-application services authorizedFifth Avenue South design decision
Verified: The April 3, 2025 minutes establish the three motions and named votes shown above. Resolution 2026-15857 later authorized a $310,702 Phase 1 agreement with Kimley-Horn plus a $20,000 owner's contingency allowance, for total authorized exposure up to $330,702.
Not established: The cited records do not identify or authorize a Phase 2 for this project. These records do not establish construction, final cost, completion or individual motive.
CRA-S05 · CRA-S17 · CRA-S18Applications reportedRiver Park residential improvement program
Verified: At the April 3, 2025 meeting, the CRA administrator reported five applications received in 2024. In the same meeting, the chair orally referenced 32 qualifying homes.
Not established: Applications and potentially qualifying homes are different measures. The meeting record does not support publishing a participation percentage, completed-home count or beneficiary count from those two figures.
CRA-S05 · CRA-S11Priced professional-services proposal; approval and execution unresolvedRiver Park East infrastructure improvements
Verified: The July 2026 procurement record identifies Pape-Dawson as the selected firm. A September 9, 2026 City memorandum prices the proposed agreement at $2,031,448: $1,219,708 from the CRA Trust Fund, $336,368 for water and $475,372 for wastewater/reclaimed water.
Not established: The reviewed agenda and memorandum do not establish that the CRA or City Council approved the agreement, that it was executed, that any amount was paid, or that construction was awarded or completed.
CRA-S19 · CRA-S20 · CRA-S21 · CRA-S26 · CRA-S27Separate authorization and audited expense records10th Street North acquisition records
Verified: The January 11, 2024 City Council minutes authorize a $4.9 million purchase of approximately 0.568 acres at 160–190 10th Street North. Separately, the FY2024 audited CRA statements report a $4,910,196 land-acquisition expense for 170 10th Street North.
Not established: The reviewed records do not establish that the two address labels identify the same acquisition. Neither record by itself establishes a completed public project or long-term delivery result.
CRA-S07 · CRA-S15Negotiation and condition assessmentStillwater Cove acquisition discussion
Verified: City-hosted April 3, 2025 minutes marked DRAFT report a $23.5 million seller counter, an approximately $4.8 million consultant estimate to correct deficiencies, 95 units and 13 structures described as 56 years old.
Not established: The record does not establish a completed acquisition. City records also conflict on unit count and acreage, so no definitive acreage is published here.
CRA-S05 · CRA-S23